The client from Kyrgyzstan plans to use the abundant resources of the cow manure. Therefore, they requested from us by e -mail details about Lines for the production of organic fertilizers from cow manure by annual performance 50 000 ton. He hopes to process traditional agricultural waste into products with high added value. Achieve multiple improvement of economic, environmental and social benefits. After a series of detailed negotiations, the customer from Kyrgyzstan decided to cooperate with us. A line for production was acquired by organic fertilizer from cow manure by annual performance 50 000 tons at our factory. It was worth it 50 000 dollars. If you are interested in investing in the industry production of fertilizers. Intend to process your agricultural waste into organic fertilizers, as a client from Kyrgyzstan. Welcome, Contact us, To get a production plan, which suits you!
Get an individual solution !
What equipment includes a production line for organic fertilizer from the cow manure of the customer from Kyrgyzstan by annual performance 50 thousands of tons worth 50 thousands of US dollars?
To satisfy the annual needs of customers in Kyrgyzstan in production 50 000 tons of organic fertilizers from cow manure. We provide a complete set of modern equipment for the production of organic fertilizers, including:
- Crushing and mixer: used for preliminary processing of cow manure. Bring raw materials to a state, suitable for fermentation.
- Aerobic fermentation capacity: Equipped with an automatic rotation and temperature control system. Help him speed up the fermentation process.
- Granulator: turns enzyme materials into homogeneous particles of organic fertilizers. Improve fertilizer ease of use.
- Drying and cooling system: provides stability and storage of granules of fertilizers from cow manure.
- Automatic packaging machine: can pack products of various specifications in accordance with market demand.

How long does it take to produce and delivery of equipment for this line for production organic fertilizer from cow manure?
Due to hard temporary requirements of customers from Kyrgyzstan. The production department of our plant immediately after receiving the order organized production:
- Production period. It takes approximately 8 weeks. This includes the completion of the manufacture and operational tests of all equipment.
- Preparation for sending. After completion of production, After a strict quality check, The equipment will be packaged and ready to send during 2 weeks.
- Time of transportation. Design and planning in accordance with the transportation route. Delivery of equipment for the production of cow manure from our plant to the customer facility in Kyrgyzstan occupies about 4 weeks. From land to sea transport, and then for ground transport.

Three main problems, which we encountered when installing a line for the production of organic fertilizers from cow manure, and their solutions!
1. Restrictions on the location of the equipment:
- Problem: space on the territory of the client is limited, What can affect the reasonable layout and installation of equipment for the production of cow manure.
- Solution: We sent engineers in advance for conducting checks on the spot. Adjust the plan for installing equipment in accordance with the real situation of Kyrgyz customers. Make sure, that all the equipment works correctly.
2. Insufficient experience of local technical personnel:
- Problem: Local personnel lack experience in operating large modern equipment.
- Solution: We organized a series of training classes. Includes equipment operation, Regulatory maintenance and elimination of malfunctions. Help local technical specialists quickly master the skills of using production lines equipment.
3. The influence of climatic conditions on fermentation:
- Question: Climate change in Kyrgyzstan affects the temperature regime of fermentation processes.
- Solution: We added a temperature control system to the fermentation tank. Make sure, that appropriate temperature Browning can be maintained in different seasons. Increasing productivity for customers in Kyrgyzstan.
Thanks to the setting of scientific equipment, effective production and delivery processes, as well as a timely and effective solution to problems. We have ensured a smooth development of the project. The customer from Kyrgyzstan for some time put into operation line for the production of organic fertilizers from cow manure. I am very pleased with us. We were also told, that if in the future there is a need to purchase equipment to expand the scale, They will contact us as soon as possible. If you are interested in investing in a fertilizer production line, Contact us. You can also visit Our factory And check the car.